Newsletter — July 2018

Over 62,000 properties able to connect to the fibre network

Topics in this edition:

  • Map updated – some AltNet details now shown
  • Contract 3 update
  • £1m Growth Deal funding secured
  • Local Full Fibre Networks Challenge Fund (LFFN)
  • Copy for your own website or newsletter
  • Questions and Answers

 

Map updated – some AltNet details now shown

Our map has been updated. The latest version reflects the following changes:

  • New data from Openreach. The new data reflects a complete overhaul of the records that are held by Openreach. Some premises that were previously unknown have now been marked up according to their current status, whilst others that actually have superfast speeds available but were not marked as such have also been updated. If you still have an amber triangle on your property, please get in touch with us, even if you have done so before
  • Some of the providers (AltNets) have given permission for us to show their areas of coverage. These are denoted by a letter inside the pink circle. Where there is no letter we have not been given permission to identify the provider
  • Contract 2 defined. Purple stars denote where we believe that Contract 2 coverage should reach. However, as the data for Contract 2 was only provided down to postcode level we have had to take a best estimate on this. Contract 2 completes at the end of 2018, and more information can be found on our rolling 12-month plan
  • Contract 3 coverage is clearly defined. As we have property-level information for Contract 3, we have been able to mark the map more accurately right down to property level. See below for more information about Contract 3

The new map can be found at: www.cswbroadband.org.uk/latestmap

Contract 3 update

We are starting to see some of the very early survey information coming through for Contract 3. However, at this stage we still don’t have any detail as to where work will be starting. Contract 3 is very different from what has gone before:

  • We will be getting information down to property-level, and this has been reflected on our maps for some time now, so that you can see if your property is due for upgrade under Contract 3 (as marked with a yellow star)
  • There will be increasing amounts of Fibre to the Premise (FTTP) in Contract 3, this brings its own challenges as FTTP involves far more civil engineering and so blocked ducts issues etc increase exponentially
  • Contract 3 covers a much wider area than previously, as we will be working in areas of Coventry for the first time
  • Contract 3 has a very short programme time. Under the terms of the contract with Openreach all work should be completed before the end of 2019

Taking into account the above factors, we hope to be able to announce areas as work starts (as previously) but will not be giving proposed completion dates, except that all work to be done under the contract should be complete by the end of 2019.

As previously, as the service goes live in each area we will be emailing those people for whom we have details in our database. That is why it is particularly important to make sure that we have your current details, and to encourage others to register. Simply visit www.cswbroadband.org.uk/register

£1m Growth Deal funding secured

We have now signed and sealed the agreement for £1m Growth Deal funding through the Coventry and Warwickshire Local Enterprise Partnership. This forms the final part of the funding jigsaw for Contract 3.

Local Full Fibre Networks Programme

Due diligence work has been ongoing, and we are now working towards issuing the Invitation to Tender during the autumn.

Copy for your own website or newsletter

We have short articles of around 300 words that can be downloaded to use in your own newsletters of on websites. These are updated monthly.

Questions and Answers

Here are some of the Q&A’s raised recently. Our website has a full set of Q&As, which are regularly updated.

Wouldn’t it make more sense to do all work in an exchange area at the same time?

This is not as straightforward as it may appear. We are about to start work on Contract 3, with Contract 2 still running. Throughout the project we have done what is possible as funding becomes available. Inevitably, this means that some areas will be later in the programme than others. This may be because some are harder to reach, or because they do not score highly on our benefits index. The index was developed at the outset of the project and prioritises areas across the whole project area.

The priorities for the project are to:

  • ensure a network deployment that contributes the most to the underlying fibre infrastructure across the sub-region
  • remove the barrier of connectivity for businesses to do business in the sub-region
  • develop a mechanism that ensures that local outcomes reflect the amounts contributed
  • benefit the maximum number of citizens.

The key one of these priorities is to get the fibre as far as possible, therefore not all infrastructure off a single exchange will be upgraded at the same time.

Should we go it alone and look for a community solution?

To see if anything is planned in your area, either through this project or from commercial providers, use our unique property checker, which shows the currently planned status (down to property level) up to the end of 2019.

You simply need to enter your postcode and you will then see a list of premises and their status. The information was largely derived from the Open Market Review and Public Consultation that we carried out in preparation for the Contract 3 procurement.

If the coverage has been promised by the commercial provider, then we are bound by commercial confidentiality and cannot give further details. However, if the upgrades are planned through the CSW Broadband project then you can see the status on our latest map and on the Rolling 12-Month Plan

To see if anything is planned in your area, either through this project or from commercial providers, use our unique property checker, which shows the currently planned status (down to property level) up to the end of 2019.

You simply need to enter your postcode and you will then see a list of premises and their status. The information was largely derived from the Open Market Review and Public Consultation that we carried out in preparation for the Contract 3 procurement.

If the coverage has been promised by the commercial provider, then we are bound by commercial confidentiality and cannot give further details. However, if the upgrades are planned through the CSW Broadband project then you can see the status on our latest map and on the Rolling 12-Month Plan

Before considering a community-funded scheme you should bear in mind that these take time to organise, and require local activists to lead the project. Having said that, it is entirely possible for a community to decide to raise funds and employ their own solution.

You should bear in mind that smaller suppliers do not always have the resilience of the larger companies. If you were to go with your own solution and employed a small company, then you could be facing sustainability issues further down the line.

You should also be aware that once an area has superfast broadband then our project may consider it to have turned grey on the map and may no longer consider it for inclusion under our funding.

On the other hand, if it is not considered to be a grey area we may later come along and upgrade the network, which could cut across the business case for any community-led solution.

One final consideration is whether your chosen solution will offer a wholesale network. This means that any Internet Service Provider can use the network to provide services to its customers.

By offering a range of providers the idea is that there will be competition which will lead to a choice of packages and a range of price-points. You will not have that with a single-supplier network.

You could, of course, choose to pay Openreach, or another major provider, to upgrade the infrastructure in your area, but the costs are likely to be significant. Should you choose to follow this route then you may want to take a look at the Community Fibre Partnerships website.

Of course, any community solution will need to be paid for! A good place to start is the Government’s Gigabit Voucher Scheme. Gigabit vouchers can be used by small and medium-sized businesses and the local communities surrounding them, to contribute to the installation cost of a gigabit capable connection.

One gigabit is the same as 1,000 megabits – so it’s a big leap forward in connection speeds that could benefit you and your business into the future.

Businesses can claim up to £3,000 against the cost of connection either individually or as part of a group project. Residents can benefit from the scheme as part of a group project, which also includes businesses, and can claim for a voucher of up to a value of £500 per residential premise.

Vouchers can be aggregated so that if, for example, a village or wanted to upgrade its connectivity then as long as there are businesses involved the vouchers can be pooled together to form one project covering the entire area. This would ensure best value for all concerned and would reduce costs overall.

To set up a local project it would be necessary to go through a supplier (as with single user vouchers). It is expected that the combined value of vouchers claimed by businesses in a scheme will be greater than the combined value of the residential vouchers. For the purpose of the scheme, a business could be someone operating from home or, potentially, working from home.

We have been getting some good reports from people who have moved to mobile broadband. Some are achieving speeds of around 70 Mbps! This technology relies on a good mobile broadband connection so it is important to use the mobile coverage checkers available on mobile broadband supplier websites before committing.

You can access a mobile broadband connection by subscribing to a data plan with your chosen mobile operator; this can usually be done using a mobile device, a dongle, or a 4G router.

When considering this option, it is important to take into consideration your data usage. Searching around for an unlimited data package can pay off, especially if you do a lot of streaming or playing videos on YouTube.

You can find more frequently asked broadband questions on our website.

CSW Broadband now on social media – come and join the conversation

We are now on the major social media channels and are already creating a buzz. Join in for up-to-date information and an opportunity to influence how the project develops:

Follow us on Facebook 

Follow us on Twitter

Follow us on LinkedIn

Posted in Project News, Newsletter Archive | Comments closed

AltNets Contribute to Broadband Coverage

For the first time, the CSW Broadband Project is able to show on the project map some of the AltNets (Alternative Network Providers) who have, or will be, providing superfast speeds to properties in Coventry, Warwickshire and Solihull.

Before going out to tender for Contract 3, CSW Broadband asked all known providers where they have existing coverage, or are planning to provide superfast coverage, by the end of 2019.

The information was provided in strict commercial confidence, so until now it has not been possible to tell people who will be providing superfast broadband in their area.

Things are changing, and some of the smaller providers (known as AltNets) have now given permission for their current and planned superfast coverage to be displayed. The information is shown on the CSW Broadband website at: www.cswbroadband.org.uk/latestmap

Properties shown with a purple star are part of the CSW Broadband Contract 2, which is due to complete at the end of 2018. Contract 3 properties are shown with a yellow star, and should be complete by the end of 2019.

Those properties that are to be covered by AltNets are shown with a pink circle and, where the information can be publicised, a letter will denote the AltNet provider for each property.

Unfortunately, some of the AltNets (and major providers) have chosen not to make public the areas that they intend to cover.

Cllr Kam Kaur, Cabinet Portfolio Holder for Customer and Transformation for lead partner, Warwickshire County Council, said: “Being able to display this information is great news. For the first time, people whose homes and businesses are to be covered by Altnets can see (in most cases) who should be providing the coverage and so can contact the provider directly for updates.

“CSW Broadband will continue to carry out annual monitoring of the coverage provided by AltNets and, if they are not able to meet their stated ambitions then the CSW Broadband team would have the option to de-scope parts of the area, which could then be brought into the CSW Broadband project should further funding become available”.

For regular updates about the CSW Broadband project residents and businesses are urged to register at: www.cswbroadband.org.uk/register

Posted in Project News | Comments closed

Newsletter — May 2018

Over 61,000 properties able to connect to the fibre network

Topics in this edition:

  • General Data Protection Regulation (GDPR)
  • Latest modelling received from Openreach
  • Local Full Fibre Networks Challenge Fund (LFFN)
  • Gigabit vouchers scheme extended – could you upgrade your area using these?
  • How to save money on Amazon
  • Copy for your own website or newsletter
  • Questions and Answers

 

General Data Protection Regulation (GDPR)

One of the biggest changes to UK data privacy law comes into effect on 25 May 2018. The General Data Protection Regulation, also known as GDPR, means that you’ll have more control over how your data is used and it ensures that organisations protect your personal data better.

To reflect these changes and new obligations, we’ve updated our privacy notice which now tells you what we do with your personal data, how it’s used and your rights as an individual under the new law. The new privacy notice will be available at https://www.cswbroadband.org.uk/about-the-project/data-protection-gdpr/

Latest modelling received from Openreach

The CSW Broadband team has finally received the latest modelling from Openreach. This takes into account the fact that Contract 3 was originally split into 3 Lots, which were all won by BT after a very thorough EU procurement exercise.

The modelling won’t change which premises are to be covered, but it does give a clearer indication of the sequencing of the rollout. Our data team are now working on the information and we will be updating the website in due course.

Local Full Fibre Networks Challenge Fund (LFFN)

Members of the CSW Broadband team went to London recently to present on our proposals. The information was well received, and the due diligence process is continuing. Although we still don’t know whether the bid will ultimately be successful, we now have the confidence to commence the early stages of the procurement process.

To that end, a Suppliers Day was held on 16 May 2018. A number of local and national suppliers were represented and a good level of interest was shown in the project, so that we now have confidence as we move into the procurement stages that we are likely to get good quality bids coming forward.

Gigabit voucher scheme extended – now includes residential

Gigabit vouchers can be used by small and medium-sized businesses and the local communities surrounding them, to contribute to the installation cost of a gigabit capable connection. One gigabit is the same as 1,000 megabits – so it’s a big leap forward in connection speeds that could benefit you and your business into the future.

Businesses can claim up to £3,000 against the cost of connection either individually or as part of a group project. Residents can benefit from the scheme as part of a group project, which also includes businesses, and can claim for a voucher of up to a value of £500.

Vouchers can be aggregated so that if, for example, a village or wanted to upgrade its connectivity then as long as there are businesses involved the vouchers can be pooled together to form one project covering the entire area. This would ensure best value for all concerned and would reduce costs overall.

To set up a local project it would be necessary to go through a supplier (as with single user vouchers). It is expected that the combined value of vouchers claimed by businesses in a scheme will be greater than the combined value of the residential vouchers.

For full details about whether you are eligible for a voucher and to connect you to a full fibre broadband supplier, go to: https://gigabitvoucher.culture.gov.uk

Please note: CSW Broadband has no involvement in the administration of this scheme, and we are unable to respond to queries about it.

How to save money on Amazon

Most of us shop on Amazon at some point as it is just so convenient! However, did you know that there are ways to save a considerable amount of money? You just have to be savvy to the various tips and tricks that the pros use.

There is a great article on MSN which gives lots of ideas to save money and, let’s face it, we’re all up for a bargain!

Copy for your own website or newsletter

We have short articles of around 300 words that can be downloaded to use in your own newsletters of on websites. These are updated monthly.

Questions and Answers

Here are some of the Q&A’s raised recently. Our website has a full set of Q&As, which are regularly updated

How do I switch to a different broadband provider?

You may wish to transfer suppliers for a variety of reasons, such as:

  • Poor quality of service
  • You need additional features that your current internet service provider (ISP) does not offer
  • You think the deal you are subscribed to is not providing good value for money
  • You are moving house/business premises

First of all, check if the contract period you signed for with your existing supplier has expired. Contracts are generally for either 12 or 18 months. Most contracts require you to give a month’s notice, even after the initial 12 or 18 months.

If it hasn’t expired, you may be liable for a cancellation fee or even the balance of the fee until the contract runs out. It’s your choice if you decide you want to buy yourself out of a contract that hasn’t yet expired.

It is important that you check that the new service you wish to sign up to is available in your area.

There are impartial sources of advice, such as:

You can also use various comparison websites to check this – we’ve listed a few below. Please remember that comparison sites work by receiving a commission from the ISPs and may not list all of the available options. Therefore you may want to try several such sites before making a decision.

Can CSW Broadband influence how much suppliers charge for their services?

We have no influence over the prices charged by commercial providers. Our role is to extend the wholesale fibre network as far as possible, and we are doing this through the contracts that we hold with BT Openreach.

As access to the network is available to all suppliers on an equal basis it is a purely commercial decision on the part of an ISP as to which packages they offer and at which price range.

The best thing is to shop around for a deal that is right for you. Please remember that price comparison sites work by receiving a commission from the ISPs and may not list all of the available options.

Therefore, you may want to try several such sites before making a decision or for independent advice got to MoneySavingExpert.com.

You can find more frequently asked broadband questions on our website.

CSW Broadband now on social media – come and join the conversation

We are now on the major social media channels and are already creating a buzz. Join in for up-to-date information and an opportunity to influence how the project develops:

Follow us on Facebook 

Follow us on Twitter

Follow us on LinkedIn

Posted in Project News, Newsletter Archive | Comments closed

Newsletter — April 2018

Over 61,000 properties able to connect to the fibre network

Topics in this edition:

  • Local Full Fibre Networks Challenge Fund (LFFN)
  • EAFRD
  • Gigabit vouchers scheme extended – now includes residential properties
  • Broadband on new developments
  • What does Google know about you?
  • Copy for your own website or newsletter
  • Questions and Answers

Local Full Fibre Networks Challenge Fund (LFFN)

We were informed just before Easter that our bid to the LFFN has been successful, subject to due diligence. Team members will be going to London at the end of April to meet the LFFN team and to answer questions arising from the bid. It is not known when we will hear the final outcome.

The CSW Broadband team are now investigating procurement options. We will need to procure the Public Sector Building upgrades, as per the bid, which is essentially a typical public sector procurement exercise.

However, we will also need to ensure that the bidders advise what local coverage of residential and business properties they expect to achieve, even though that is not part of the work that is funded through the project.

Market engagement has already started, as we need to understand what suppliers are realistically able to deliver as it would be a waste of time for them to specify something that is simply not deliverable.

EAFRD

EAFRD focusses on connectivity to rural businesses that would not otherwise be upgraded. The bid has been delayed as we are awaiting details from Openreach of the additional coverage that they are putting into Contract 3, so that we can then establish where the final eligible premises will be.

With the deadline of 31st May fast approaching, we are doing all that we can to ensure that a fully compliant and well-argued bid is submitted in good time.

Gigabit voucher scheme extended – now includes residential

In the Spring Statement the government committed to a vision of a full fibre Britain. As part of this commitment, a £67 million Gigabit Broadband Voucher Scheme has been announced.

This is an extension of the pilot scheme that was previously run in Coventry and Warwickshire, but with one important change – residential premises can now also benefit.

Gigabit vouchers can be used by small and medium-sized businesses and the local communities surrounding them, to contribute to the installation cost of a gigabit capable connection.

Businesses can claim up to £3,000 against the cost of connection either individually or as part of a group project. Residents can benefit from the scheme as part of a group project, which also includes businesses, and can claim for a voucher of up to a value of £500.

One gigabit is the same as 1,000 megabits – so it’s a big leap forward in connection speeds that could benefit you and your business into the future.

For full details about whether you are eligible for a voucher and to connect you to a full fibre broadband supplier, go to: https://gigabitvoucher.culture.gov.uk

Please note: CSW Broadband has no involvement in the administration of this scheme, and we are unable to respond to queries about it.

Broadband on new developments

We are seeing almost daily enquiries from owners of properties on new developments asking when we will be going to their areas. The simple answer, generally speaking, is that we won’t!

Before CSW Broadband went out to tender in 2017 for Contract 3, we carried out an Open Market Review in 2016. Under this process, suppliers were sent lists of premises that appeared at that time on the Ordnance Survey AddressBase.

The data for this originates from the District or Borough Authorities, who enter the information into the Property Gazeteer. Therefore, the data can only include homes that have been built and registered, and is only as up-to-date as the District or Borough Authority data at that time.

If a property had not yet been built, or was not registered, then it could not be included in the data that was sent to suppliers.

It is not unreasonable to expect the developers to include broadband in their on-site infrastructure, and many do, however many people buy homes and expect that broadband will be provided, only to be disappointed once they move in.

To complicate the issue, there is an EU standard that required newer homes to be built as “internet ready”, so they will have network wiring around the property. However, that does not necessarily mean that there will be any connectivity from the property to the fibre network.

Buyers of any property, new or old, are strongly recommended to check the broadband connectivity situation, if it is important to them, before they buy. Don’t just take the salesperson’s word for it!

What does Google know about you?

There has been a lot in the media lately about personal data and the extent to which it is harvested, kept and shared by the services that we use every day.

Not all of this is necessarily harmful or malevolent – and some of it is essential if we are to be able to make sure of all those shortcuts and timesaving features that we take for granted.

However, it does help to know what is being kept so that you can make some informed choices.

This article on MSN gives an account of how one person tracked what data Google had harvested about him. This included (if you use these services):

  • Everywhere that you visit from the day that you turn on your telephone
  • Search and phone histories
  • Creating personalised advertisement profiles based on the websites visited
  • Every App and Extension used, who you talk to and who you follow on social media
  • All of your YouTube history – so they know what you are interested in and any potential life changes
  • Your bookmarks, email contacts, photos, who you’ve bought products from
  • Your calendar, location history, music you’ve listened to, Google books you’ve purchased, phones you’ve owned, steps you walk in a day …

You get the picture!

We would re-iterate that allowing Google to store this data enables you to make free use of some very sophisticated FREE services that we all take for granted. However, if you would like to know more, including how to stop the storage of data, this very interesting article will tell you more.

Google are not the only company doing this, and reading the article may give you the opportunity to consider what other companies might be collecting, and then to take a considered decision before clicking on the button to simply accept the terms and conditions.

Copy for your own website or newsletter

We have short articles of around 300 words that can be downloaded to use in your own newsletters of on websites. These are updated monthly.

Questions and Answers

Here are some of the Q&A’s raised recently. Our website has a full set of Q&As, which are regularly updated.

Once my new fibre cabinet is connected to the exchange (or FTTP is enabled), what then?

That is entirely up to you. We are installing a wholesale network, which means that once your cabinet has gone live (or FTTP has been enabled) any Internet Service Provider (ISP) can offer you high speed broadband (subject to availability) and there are a wide range of packages available.

Do check though that you are able to actually achieve the speeds that are advertised as the geographic issues mentioned on our website will apply in cases where a new cabinet is involved. You can check which structure you are connected to by using the BT DSL checker.

Our handy ‘How to use the BT Line Checker’ webpage will help you make sense of the DSL Checker results.

For the best results, you will need to be able to enter a BT landline number for your property. If you do not have this then you can use your address, but it may be less accurate. Do not use the postcode checker as that covers too wide an area to be of any use.

Don’t forget that you will need to upgrade to a superfast broadband package through your chosen ISP. The access is on a wholesale basis, which means that any ISP can use the infrastructure to provide their services.

You will also need to check out broadband packages carefully to get the one that is right for you. For impartial advice go to the Money Saving Expert website.

We have leaflets that can be distributed to every property that is connected to the upgraded cabinets. To find out more please visit our Become a Community Champion web page.

My phone line is connected to a cabinet that is not upgraded. How can I get it moved to a fibre-enabled cabinet?

It is an operational matter for BT as to which cabinet they connect your landline to. There is a legal obligation to provide a copper telephone connection, but not for a fibre broadband connection.

In some areas, BT are carrying out CuRE (Copper Re-Arrangement) work, which does involve moving lines from one cabinet to another. In other areas we are seeing FTTP (Fibre to the premise) installations, in which case the cabinet is irrelevant.

You can check which structure you are connected to and what speed is available to you now by using the BT DSL checker.

As mentioned earlier, for the best results you will need to be able to enter a BT landline number for your property. If you do not have this then you can use your address, but it may be less accurate. Do not use the postcode checker as that covers too wide an area to be of any use.

To see if anything is planned in your area for the future, either through this project or from commercial providers, use our unique property checker, which shows the currently planned status (down to property level) up to the end of 2019.

This information was largely derived from the Open Market Review and Public Consultation that we carried out in preparation for the Contract 3 procurement. If the coverage has been promised by the commercial provider, then we are bound by commercial confidentiality and cannot give further details.

However, if the upgrades are planned through the CSW Broadband project then you can see the status on our latest map and on the Rolling 12-Month Plan.

You can find more frequently asked broadband questions on our website.

CSW Broadband now on social media – come and join the conversation

We are now on the major social media channels and are already creating a buzz. Join in for up-to-date information and an opportunity to influence how the project develops:

Follow us on Facebook 

Follow us on Twitter

Follow us on LinkedIn

Posted in Project News, Newsletter Archive | Comments closed

£5.5m Ultrafast Broadband Bid Successful

The CSW Broadband Project, which is bringing faster broadband to those parts of Coventry, Solihull and Warwickshire where there are no commercial plans for upgrades, has learned that it has been successful in its bid of over £5.5m to the Local Full Fibre Networks Challenge Fund.

The bid will invest in bringing 1Gbps-capable full fibre networks right to the most expensive and hard-to-reach public buildings across the project area. These could include rural schools, fire stations and libraries.

The idea is that the project will go out to tender for a contractor to carry out the public sector building connectivity upgrades, and that the successful bidder will, at their own cost, upgrade connections to residential and business properties along the fibre route.

The Gigabit Voucher Scheme, which was piloted in Coventry and Warwickshire will now continue as a national scheme.

Councillor Kam Kaur, Cabinet Portfolio Holder for Customer and Transformation for lead partner, Warwickshire County Council, said: “This is a real opportunity to improve connectivity at some of the hardest-to-reach schools and other public buildings. The Ultrafast, Gigabit-capable, network will be a real step-change beyond the existing infrastructure and will bring exciting education, business and other opportunities to those who are able to connect to the new network.

“It is early days, and we do not yet have the detail of what has been awarded, but the CSW Broadband team hopes to be in a position to scope the work and to start the procurement process over the next few months. Further information will be given in the project’s monthly e-newsletters, along with details of the contracted superfast broadband rollout in Coventry, Solihull and Warwickshire.”

To register for updates about the CSW Broadband project visit: www.cswbroadband.org.uk

Posted in Project News | Comments closed

Newsletter — March 2018

Over 61,000 properties able to connect to the fibre network

Topics in this edition:

  • BT asked to model an additional £1.9m coverage
  • First surveys for Contract 3 to start shortly
  • Local Full Fibre Networks Challenge Fund (LFFN)
  • EAFRD
  • Changes within the team
  • Copy for your own website or newsletter
  • Questions and Answers

 

BT asked to model an additional £1.9m coverage

Regular readers will recall that Contract 3 has a potential maximum value of £20m, and that last year’s Invitation to Tender carried a value of £15m. Following an extremely rigorous procurement process, BT won all three Lots.

As these bids represented excellent value for money and came to a total of less than £15m, we have now asked Openreach to model an additional £1.9m of coverage to bring the value of the current contract back up to the original £15m.

We expect to receive the return any day now, and the data team will then begin the laborious task of checking the data and creating the new maps. This work will take several weeks, and we hope to be able to publish new maps showing the additional coverage in May/June of this year.

First surveys for Contract 3 to start shortly

Residents in some areas will shortly see survey activity taking place. This is the initial stages of the work for Contract 3. It is likely to be a few months yet before we see the first structures going live.

Contract 3 is different from Contracts 1 and 2 in that we have the information down to property level, and this is displayed on our map, where yellow stars denote Contract 3 work. Contract 3 is due to complete at the end of 2019.

Local Full Fibre Networks Challenge Fund (LFFN)

We are still awaiting the outcome of our LFFN bid. It is believed that there have been a number of projects from across the country who have lodged bids for Phase 2 of the fund. This bid is very different from what has gone before.

The project requirements are to connect public sector buildings to the full fibre network (i.e. FTTP) with Gigabit-capable connections. The idea is that by taking full fibre out to public buildings, the successful contractor will then connect homes and businesses along the fibre route and in the vicinity of the newly-connected public buildings.

Our data team have compiled a compelling case, but of course we do not know what other projects may have submitted. We hope to hear the outcome of this bid in the next couple of months.

If successful, the work will be very different from what has gone before, since we will be carrying out a public-sector procurement rather than commissioning a wholesale network (which is what the BDUK project has done thus far).

As always, we’ll continue to publish information in the newsletters as we receive it.

EAFRD

Because the EAFRD bid can only go to rural areas where there is no planned coverage, we are eagerly awaiting the return from Openreach for the modelling of the additional £1.9m mentioned earlier in this newsletter. This will give us a clearer indication as to where the EAFRD bid might be able to reach.

The EAFRD bid is similar to the LFFN in that it targets specific premises, but in this case we will be looking at those hard-to-reach rural businesses that otherwise would not stand a chance of getting superfast connections.

The funding will be brought into Contract 3, so the requirement will be for a wholesale access superfast network offering a minimum of 30Mbps.

We will have to prove evidence of need, so will be contacting businesses in the relevant areas once these have been identified. The requirement is for us to provide the network, not to monitor whether a service is taken up.

Once, again, we’ll publish more information as we receive it.

Changes within the team

After many years of stability, we have seen some significant changes with the structure of the team. Our Project Executive, John Parmiter, has retired after almost 20 years working for Warwickshire County Council. John started his career as a teacher, and later became a schools’ inspector.

He then ran a project to bring ICT to Warwickshire’s schools. Later John was involved in bringing Internet connectivity to schools throughout Warwickshire.

He was involved in the BDUK project (which became known as CSW Broadband) from its earliest days, and provided excellent leadership and strategic direction to the project. John’s role has been taken over by Richard Hopkins, who comes from a strong technical and contracts management background.

Gurprit Basran, who has been Project Administrator since 2012 is also moving on to pastures new. Gurprit has been the unsung hero of the team, working behind the scenes to ensure that we have all documentation in order and that the systems are running as they should.

Gurprit has been a massive support to all of us and will be sorely missed.

As far as the day-to-day running of the project is concerned, there should be little outward evidence of the changes, although we will all miss these two key members of the team and wish them both every success in the future.

Copy for your own website or newsletter

We have short articles of around 300 words that can be downloaded to use in your own newsletters of on websites. These are updated monthly.

Questions and Answers

Here are some of the Q&A’s raised recently. Our website has a full set of Q&As, which are regularly updated.

Once my new fibre cabinet is connected to the exchange (or FTTP is enabled), what then?

That is entirely up to you. We are installing a wholesale network, which means that once your cabinet has gone live (or FTTP has been enabled) any Internet Service Provider (ISP) can offer you high speed broadband (subject to availability) and there are a wide range of packages available.

Do check though that you are able to actually achieve the speeds that are advertised as the geographic issues mentioned on our website will apply in cases where a new cabinet is involved.

You can check which structure you are actually connected to by using the BT DSL checker. Our handy ‘How to use the BT Line Checker’ webpage will help you make sense of the DSL Checker results.

For the best results you will need to be able to enter a BT landline number for your property. If you do not have this then you can use your address, but it may be less accurate. Do not use the postcode checker as that covers too wide an area to be of any use.

Don’t forget that you will need to upgrade to a superfast broadband package through your chosen ISP. The access is on a wholesale basis, which means that any ISP can use the infrastructure to provide their services.

Don’t forget that you will need to check out broadband packages carefully to get the one that is right for you. For impartial advice go to the Money Saving Expert website.

We have leaflets that can be distributed to every property that is connected to the upgraded cabinets. To find out more please visit our Become a Community Champion web page.

My phone line is connected to a cabinet that is not upgraded. How can I get it moved to a fibre-enabled cabinet?

It is an operational matter for BT as to which cabinet they connect your landline to. There is a legal obligation to provide a copper telephone connection, but not for a fibre broadband connection.

In some areas, BT are carrying out CuRE (Copper Re-Arrangement) work, which does involve moving lines from one cabinet to another. In other areas we are seeing FTTP (Fibre to the premise) installations, in which case the cabinet is irrelevant.

You can check which structure you are actually connected to and what speed is available to you now by using the BT DSL checker.

For the best results you will need to be able to enter a BT landline number for your property. If you do not have this then you can use your address, but it may be less accurate. Do not use the postcode checker as that covers too wide an area to be of any use.

To see if anything is planned in your area for the future, either through this project or from commercial providers, use our unique property checker, which shows the currently planned status (down to property level) up to the end of 2019.

The information was largely derived from the Open Market Review and Public Consultation that we carried out in preparation for the Contract 3 procurement. If the coverage has been promised by the commercial provider, then we are bound by commercial confidentiality and cannot give further details.

However, if the upgrades are planned through the CSW Broadband project then you can see the status on our latest map and on the Rolling 12-Month Plan.

You can find more frequently asked broadband questions on our website.

CSW Broadband now on social media – come and join the conversation

We are now on the major social media channels and are already creating a buzz. Join in for up-to-date information and an opportunity to influence how the project develops:

Follow us on Facebook 

Follow us on Twitter

Follow us on LinkedIn

Posted in Project News, Newsletter Archive | Comments closed

Newsletter — February 2018

Nearly 61,000 properties able to connect to the fibre network

Topics in this edition:

  • Remainder of Contract 2 rollout announced
  • What’s coming up?
  • Crystal ball required?
  • Carillion telent – update
  • Hoax Slayer
  • Information for parish council websites – update
  • Copy for your own website or newsletter
  • Questions and Answers

Wave 9 rollout announced

We have now announced the areas to be upgraded in Wave 9. These appear on our Rolling 12-month Plan, where you can check progress on all structures announced to date. This is the final Wave for Contract 2, which is scheduled to be completed before the end of the year.

We are planning a major update of the mapping and the website during the spring.

What’s coming up?

Contract 3 work will be starting shortly. Initial surveys will be underway, so you may see people out and about. Please bear in mind that the survey is no indication of when work will be starting on the installations. Contract 3 brings a far higher proportion of FTTP, which is why we are hoping that an early start can be made.

Crystal ball required?

Who knows what the future will bring? The CSW Broadband team has submitted an application to the recently announced Local Full Fibre Network Challenge Fund (LFFN). This bid is somewhat different from the BDUK programme. It proposes 1Gb-capable full fibre networks to public buildings in Coventry, Solihull and Warwickshire.

The intention is that the procurement will be a straightforward public sector procurement, with the bidders being asked to state how many businesses or residential premises along the route will also be offered a full fibre service.

The project will not actually pay for the connections to these additional premises, but the project will stimulate the market by bringing the full-fibre network out to areas that would not otherwise have been upgraded to FTTP. The project will also include an extension of the Gigabit Voucher Scheme, that is currently being run by Central Government. We should hear the outcome of this bid during the spring.

In addition, at its budget setting on 7th February, Warwickshire County Council agreed a sum of £200,000 to provide advisers to help teachers in LFFN schools to make best use of the new technologies, and to ensure that safeguarding measures are fully understood and implemented. The schools can also act as a community hub, so that parents and local residents can also benefit from the adviser’s knowledge.

We still are a long way from securing the LFFN funding, and as we have more information about this project we will, of course, include it in future newsletters.

CSW Broadband are also preparing a bid for EAFRD (European Agricultural Fund for Rural Development) funding. This will cover those areas of Warwickshire and Solihull that currently cannot achieve superfast speeds. Again, we would hope to hear the outcome of the bid during the spring.

In both cases, achieving the funding is only the first part of the jigsaw, for the LFFN a full OJEU procurement would need to be carried out, whereas the EAFRD money can be added to Contract 3 through Change Control processes.

The currently planned Contract 3 works are due to be completed by the end of 2019.

Carillion telent – update

Since the start of the project, Carillion telent has carried out work on behalf of BT. Given the recent news headlines about Carillion, BT were asked for an update on how this situation might affect the project.

We have been assured that telent will be taking over responsibility for the contracted works, and that the same personnel will be continuing to work on the CSW Broadband project. We have been sent a link to a full statement, which can be found at: https://telent.com/news-media/news/carillion-telent-joint-venture-statement

Hoax Slayer

Hoax Slayer is a great resource to find out about the latest online scams, or to check if an email that you have received is genuine. We hear so much these days about various phishing emails (an email that pretends to come from a trusted source and seeks to gather your personal data and passwords); scams and online frauds that it can be difficult to know what’s true and what isn’t. Hoax Slayer is a great FREE resource that explodes the latest myths, and provides a search facility so that you can paste in text to see if your email is real or not.

It’s worth a read just to see how blatant some of these scams are – it does make you wonder how people can fall for some of them! However, not everybody is Internet savvy, and even those of us who think we’ve got it nailed can get caught out sometimes. For more information, visit http://www.hoax-slayer.net

Copy for your own website or newsletter

We have short articles of around 300 words that can be downloaded to use in your own newsletters of on websites. These are updated monthly.

Questions and Answers

Here are some of the Q&A’s raised recently. Our website has a full set of Q&As, which are regularly updated.

Does my service automatically change when the upgrades are complete?

No. You will have to upgrade the broadband package that you purchase to one offering superfast speeds. We are installing a wholesale network, which means that once your cabinet has gone live any Internet Service Provider (ISP) can offer you high speed broadband (subject to availability), and there are a wide range of packages available.

These will come with different products, such as films, sport and TV bundled, so it’s best to shop around. Do check before changing supplier, though, when your existing contract expires. You may have to upgrade with your current supplier in the first instance to avoid contract cancellation charges

We recommend that you check out broadband packages carefully to get the one that is right for you. For impartial advice go to the Money Saving Expert website.

Do check that you are able to actually achieve the speeds that are advertised, as the geographic issues mentioned on our website will apply in all cases. You can check which cabinet you are actually connected to by using the BT DSL checker.

For the best results you will need to be able to enter a BT landline number for your property. If you do not have this then you can use your address, but it may be less accurate. Do not use the postcode checker as that covers too wide an area to be of any use.

Can we get any help to upgrade our local network?

You can check to see if anything is planned in your area, either through this project or from commercial providers, using our unique property checker, which shows the currently planned status (down to property level) up to the end of 2019.

You simply need to enter your postcode and you will then see a list of premises and their status. The information was largely derived from the Open Market Review and Public Consultation that we carried out in preparation for the Contract 3 procurement.

If the coverage has been promised by the commercial provider, then we are bound by commercial confidentiality and cannot give further details. However, if the upgrades are planned through the CSW Broadband project then you can see the status on our latest map and on the Rolling 12-Month Plan

Before considering a community-funded scheme you should bear in mind that these take a long time to organise, and require a lot of hard work on the part of local activists. Having said that, it is entirely possible for a community to decide to raise funds and employ their own solution.

You should bear in mind that smaller suppliers do not always have the resilience of the larger companies. If you were to go with your own solution and employed a small company, then you could be facing sustainability issues further down the line.

You should also be aware that once an area has superfast broadband then our project may not be able to consider it for inclusion under future funding. On the other hand, if it is not considered to be superfast, we may later come along and upgrade the network, which could cut across the business case for any community-led solution.

One final consideration is whether your chosen solution will offer a wholesale network. This means that any Internet Service Provider can use the network to provide services to its customers. By offering a range of providers the idea is that there will be competition which will lead to a choice of packages and a range of price-points. You will not have that with a single-supplier network.

You could, of course, choose to pay BT Openreach, or another major provider, to upgrade the infrastructure in your area, but the costs are likely to be significant. Should you choose to follow this route then you may want to take a look at the Community Fibre Partnerships website.

We have been getting some good reports from people who have moved to mobile broadband. Some are achieving speeds of around 70 Mbps! This technology relies on a good mobile broadband connection so it is important to use the mobile coverage checkers available on mobile broadband supplier websites before committing.

You can access a mobile broadband connection by subscribing to a data plan with your chosen mobile operator; this can usually be done using a mobile device, a dongle, or a 4G router.

When considering this option, it is important to take into consideration your data usage. Searching around for an unlimited data package can pay off, especially if you do a lot of streaming or playing videos on YouTube.

You can find more frequently asked broadband questions on our website.

CSW Broadband now on social media – come and join the conversation

We are now on the major social media channels and are already creating a buzz. Join in for up-to-date information and an opportunity to influence how the project develops:

Follow us on Facebook 

Follow us on Twitter

Follow us on LinkedIn

Posted in Project News, Newsletter Archive | Comments closed

Winds of change – multi-million pound roll-out of superfast broadband reaches out to every corner of Warwickshire

Historic Ansley Common, Chesterton, Fulready, Goldicote, Grendon, Little Wolford, Ufton and Wibtoft among next places to benefit from CSW Broadband roll-out

The next phase of the multi-million pound CSW Broadband roll-out will have a positive impact on communities the length and breadth of the county, lead partners Warwickshire County Council and BT Group announced today.

It will make high-speed fibre broadband available to more of Warwickshire’s smallest, oldest communities, including those in some key agricultural areas.

They include Chesterton, near Warwick, famous for its landmark Grade I listed windmill, Wibtoft, near Rugby, said by historians to have links with the Roman times, and Ansley Common, which is listed in the Domesday Book and is believed to have links with Lady Godiva.

Areas of Ashorne Hill, Fulready, Goldicote, Grendon, Little Wolford and Ufton will also get access to the technology for the first time. This phase of the roll-out will also enable additional households and businesses in Berkswell to upgrade.

Engineers from Openreach – the business responsible for Britain’s largest phone and broadband network – will begin the upgrades in the next few months, and the first households and businesses will start to go ‘live’ in the Autumn.

Local households and businesses can follow the progress of the CSW Broadband roll-out and get updates via the project website and online map – www.cswbroadband.org.uk/latestmap

It also includes information about the areas to benefit from the £28 million Contract 3 expansion of CSW Broadband with BT Group, announced last Autumn. The roll-out is part of the Government’s Broadband Delivery UK (BDUK) programme.

Councillor Kam Kaur, Holder for Customer and Transformation for lead partner, Warwickshire County Council, said: “Once again the CSW Broadband project is reaching out to some of our most rural areas. Even a couple of years ago these villages could only dream of getting fibre broadband, and now it is to become a reality.

“The provision of 21st Century communications to these very rural villages will enable people not only to shop online but also use banking services and education resources that so many people take for granted nowadays. They will also be able to access a wide range of public services without the need for time-consuming and expensive car journeys – and, of course, to keep in touch with loved ones across the globe.”

Steve Haines, Managing Director of Next Generation Access for Openreach, said: “CSW Broadband is a major engineering programme which has already successfully overcome a range of technical and geographical challenges and is continuing to spread its wings to more of the most remote areas.

“Many of the homes and businesses in this next phase are served by exchange only (EO) lines which are connected directly to the telephone exchange rather than via a green roadside cabinet. In order to connect EO lines, additional roadside cabinets have to be installed and cables diverted to enable more of the county’s most remote communities to access this important technology.

“The demand for high speed broadband is increasing all the time with the internet touching virtually every aspect of our lives. Statistics show that with the growth in streaming and downloading video, fuelled by services like Netflix, YouTube and Amazon, home broadband data usage has grown at a rate of 36 per cent a year.

“Superfast broadband also breaks down barriers to doing business around Warwickshire and across the globe as it helps small businesses to find new markets, sell new products and communicate more easily and quickly with their customers, suppliers and employees.”

Because the fibre broadband network is being installed by Openreach, households and businesses have a wide choice of fibre broadband providers. Upgrades do not happen automatically. Anyone wanting to benefit need to place an order with their chosen fibre broadband provider.

Existing underground ducting is used wherever possible, minimising disruption and the need to dig up roads and pavements.

Posted in Project News | Comments closed

Newsletter — December 2017

Over 60,000 properties able to connect to the fibre network

Topics in this edition:

  • Over 60,000 premises now able to connect to the fibre network
  • Superfast connection vouchers for businesses
  • Gigabit connection grants for businesses
  • Better broadband connection vouchers
  • Parish-level mapping for parish council websites – update
  • Copy for your own website or newsletter
  • Questions and Answers

Over 60,000 premises now able to connect to the fibre network

Over 60,000 households and businesses are now able to get high-speed broadband, thanks to the CSW Broadband Project.

The pace of the roll-out and the mixture of technology being used by engineers from Openreach means dozens more properties are going ‘live’ on an almost daily basis. Many of these will be “Exchange Only” lines, or at some distance from existing fibre infrastructure, so property owners may not realise that they can now connect to the new network.

Residents and businesses are therefore urged to keep checking whether they can access the technology by checking the BT DSL checker to establish which infrastructure your property is connected to. For the best results you will need to be able to enter a BT landline number for your property.

If you do not have this then you can use your address, but it may be less accurate. Do not use the BT postcode checker as that covers too wide an area to be of any use. The How to use the BT DSL Line checker page on our website contains a handy guide to interpreting the results of the BT checker.

It is amazing to realise that, just three and a half years since the first CSW Broadband cabinet went live, over 60,000 premises can now connect to the fibre network. This is a real step-change and shows that this public investment is making massive improvements to our local infrastructure.

There is still a lot more coverage to come between now and the end of 2019, and the team are actively seeking additional funding to take the fibre network still further.

Superfast connection vouchers for businesses

Coventry​ ​and​ ​Warwickshire​ ​Chamber​ ​of​ ​Commerce​ ​has​ ​launched​ ​its​ ​new​ ​ICT​ ​Business Support​ ​service, ​ ​funded​ ​through​ ​European​ ​Regional​ ​Development​ ​Fund. The aim is to assist businesses to make the most of the technology that is available today, and to plan for the future.

To​ ​help​ ​with​ ​this,​ ​a​ ​Connection​ ​Voucher​ ​is​ ​available​ ​that​ ​will​ ​offer​ ​match-funded​ ​grants​ ​to help​ ​the​ ​SME​ ​to​ ​actually​ ​implement​ ​the​ ​change​ ​and​ ​to​ ​take​ ​advantage​ ​of​ ​the​ ​new technologies.​ ​

The​ ​voucher​ ​is to​ ​be​ ​used​ ​towards​ ​the​ ​cost​ ​of​ ​a​ ​complete​ ​end-to-end​ ​solution, including a​ ​Superfast​ ​connection​ ​to​ ​the​ ​Internet and networking​ ​within​ ​the​ ​business,​ ​either​ ​wireless​ ​or​ ​cabled,​ ​as​ ​appropriate; Equipment​ ​​to​ ​implement​ ​transformational​ ​business changes may also be eligible.

To​ ​find​ ​out​ ​more​ ​please​ ​call​ ​Coventry​ ​and​ ​Warwickshire​ ​Chamber​ ​on​ ​02476​ ​654​ ​321​ ​to speak​ ​with​ ​an​ ​advisor​ ​today. Please do not contact the CSW Broadband project about this scheme as we are not involved in the administration.

Gigabit connection grants for businesses

If you are a small or medium-sized business, you may be able to get a grant of up to £3,000 to upgrade your business broadband to a Gigabit capable connection.

The Government is testing a new Gigabit Voucher Scheme, which will provide vouchers worth up to £3,000 to support the capital costs of getting new gigabit capable connections for businesses. Coventry and Warwickshire are one of the four pilot areas.

Suppliers will be offering vouchers worth between £500 and £3000 each to local businesses, which can then be used to pay for the installation of gigabit speed connections.

The aim of the pilots is to encourage the market to extend full fibre infrastructure in the UK by increasing demand and reducing the cost to customers.

The pilot is supplier-led, meaning that customers will need to go to an approved supplier who will then deal with the administration of the scheme. Details of approved suppliers can be found at: https://gigabitvoucher.culture.gov.uk

Please note that the CSW Broadband project is not involved in the administration of this scheme, and all enquiries should be made through the above website.

Better broadband connection vouchers

Finally, if neither of the above schemes are right for you (or if you are not a business), the Government has recently announced an extension to the Better Broadband Subsidy Scheme.

If you currently experience poor broadband speeds, or are unable to obtain an affordable broadband service at all, the scheme will provide you with access to a basic broadband service that will offer speeds of at least 2 Mb per second, and usually much higher.

The scheme will ensure that no household or business will need to pay more than £400 to access a basic broadband service over a 12-month period.

If you take advantage of this scheme, your household or business will still be eligible for a superfast broadband service in the future.

Households and businesses that are eligible to take advantage of the scheme will be provided with a unique code that will cover most of the cost of the installation and commissioning of a basic broadband service including any necessary equipment.

You will be required to enter into a contract for a minimum of 12 months with one of the suppliers registered under the scheme and pay any remaining cost of installation, the monthly charge for the service they select, and any VAT payable.

The code does not have a specific fixed value but when used to obtain a basic broadband service from a registered supplier it will reduce the total cost by up to £350. The code has no other value and cannot be redeemed in any other way than through the scheme.

Households and businesses can take advantage of the scheme, if they meet the following three criteria.

  • Your home or business is not currently able to access a broadband download speed of at least 2Mb per second.
  • There are no alternative affordable broadband services available to you, which would provide a download speed of at least 2Mb per second.
  • There are no plans to provide superfast broadband to your location within 12 months of your application.

Households and businesses that apply for a subsidy will be asked to confirm there are no alternative affordable broadband services available to them that offer a broadband speed of at least 2 Mb per second.

To apply, visit the Guide to the Better Broadband Subsidy Scheme page on our website.

Parish-level mapping for parish council websites – update

Thanks to those parishes who responded to our last newsletter stating that they would be interested in parish-level mapping to go onto local websites. Out data team will be working on this over the next few months and we’ll advise in a future edition how you can access this facility.

What would help you, as a parish council, to keep your residents informed about the broadband rollout?

Please drop us an email to broadband@cswbroadband.org.uk, and we’ll develop a plan that incorporates as many of the suggestions as possible.

Copy for your own website or newsletter

We have short articles of around 300 words that can be downloaded to use in your own newsletters of on websites. These are updated monthly.

Questions and Answers

Here are some of the Q&A’s raised recently. Our website has a full set of Q&As, which are regularly updated.

What is FTTP on demand?

We have recently had a number of enquiries where the BT DSL checker suggests that a product called Fibre on Demand (FoD or FTTPoD) is available, offering speeds of up to 330Mbps.

This is NOT the same as native Fibre to the Premise (FTTP), which is being installed to many areas through this project.

It is easy to get native Fibre-to-the-Premise (FTTP) services confused with FTTPoD because the two solutions function in identical ways, although their cost, contract and deployment methods have tended to be significantly different.

In a native FTTP setup, the fibre optic cable will have been installed outside your property (e.g. down your street), which makes it fairly quick and inexpensive to get connected.

By comparison FTTPoD is designed to be requested (‘on demand‘) in Fibre to the Cabinet (FTTC) capable areas where the fibre optic cables have yet to reach specific properties. In some cases, this will attract significant distance-based construction charges (civil works) worth thousands of pounds.

Because of the high costs involved (and often the requirement for a much longer than standard contract), very few providers actually offer FTTPoD. Some that we are aware of include Cerberus Networks and FluidOne. It’s worth doing your homework as there may be others.

This is likely to remain a niche product for those who are prepared to pay the additional installation charges and a higher ongoing monthly cost.

How do I switch to a different broadband provider?

You may wish to transfer suppliers for a variety of reasons, such as:

  • Poor quality of service
  • You need additional features that your current internet service provider (ISP) does not offer
  • You think the deal you are subscribed to is not providing good value for money
  • You are moving house/business premises

First of all, check if the contract period you signed for with your existing supplier has expired. Contracts are generally for either 12 or 18 months.

Most contracts require you to give a month’s notice, even after the initial 12 or 18 months. If it hasn’t expired, you may be liable for a cancellation fee or even the balance of the fee until the contract runs out.

It’s your choice if you decide you want to buy yourself out of a contract that hasn’t yet expired.

It is important that you check that the new service you wish to sign up to is available in your area.

There are impartial sources of advice, such as:

You can also use various comparison websites to check this – we’ve listed a few below. Please remember that comparison sites work by receiving a commission from the ISPs and may not list all of the available options. Therefore you may want to try several such sites before making a decision.

You can find more frequently asked broadband questions on our website.

CSW Broadband now on social media – come and join the conversation

We are now on the major social media channels and are already creating a buzz. Join in for up-to-date information and an opportunity to influence how the project develops:

Follow us on Facebook 

Follow us on Twitter

Follow us on LinkedIn

Posted in Project News, Newsletter Archive | Comments closed

60,000 households and businesses looking forward to a fibre broadband Christmas thanks to multi-million pound CSW Broadband

60,000 households and businesses looking forward to a fibre broadband Christmas thanks to multi-million pound CSW Broadband

The CSW Broadband Project – led by Warwickshire County Council and BT Group – has delivered some early Christmas cheer by confirming 60,000 households and businesses are now able to get high-speed broadband thanks to the partnership’s multi-million pound roll-out.

The technology has recently become available in parts of Baginton, Clifford Chambers, Lower Tysoe and the Longbridge area of Warwick.

Local people are urged to keep checking whether they can access the technology by logging onto CSW Broadband’s new online map – www.cswbroadband.org.uk/latestmap – which is designed to give local households and businesses more detail than ever before about the roll-out.

The pace of the roll-out and the mixture of technology being used by engineers from Openreach – the business responsible for Britain’s largest telephone and broadband network – means more properties are going ‘live’ on a regular basis.

CSW Broadband is part of the Government’s Broadband Delivery UK (BDUK) programme.

Councillor Kam Kaur, Portfolio Holder for Customer and Transformation for lead partner Warwickshire County Council, said: “It is amazing to realise that, just three and a half years since the first CSW Broadband cabinet went live, over 60,000 premises can now connect to the fibre network. This is a real step-change and shows that this public investment is making massive improvements to our local infrastructure.

“In the early days of the project many people didn’t realise the benefits that faster broadband would bring. Now it is commonplace to stream films and music, work from home in real-time, and share massive files with people around the world. There is still a lot more coverage to come between now and the end of 2019, and the team are actively seeking additional funding to take the fibre network still further.”

Steve Haines, Managing Director of Next Generation Access for Openreach, said: “Increasingly, fibre broadband has become the ‘must have’ technology for families and businesses, which is why we’re working hard to make it available to as many people as possible, even in the most remote parts of Warwickshire.

“It’s particularly important to have access to high-speed broadband at this time of the year when many of us use the internet more than usual for leisure and entertainment. Having high-speed broadband can make online shopping and ‘click and collect’ services quick and convenient, and staying in touch with loved ones abroad much easier.”

Because the fibre broadband network is being installed by Openreach, households and businesses have a wide choice of fibre broadband providers. Upgrades do not happen automatically. Anyone wanting to benefit needs to place an order with their chosen fibre broadband provider.

Existing underground ducting is used wherever possible.

Posted in Project News | Comments closed